County · Roads & bridges
Rebuild Hamilton Road/King Street West from the CPKC Railway to the town boundary, including the Oxford Roads 9 and 10 intersection.
Ingersoll
Construction underway; December 2026 completion target- 2026 allocation
- Not established
- Named supplier
- J-AAR Civil Infrastructures Limited
- Next target
- 2026-12 · Whole-project target
- Latest update
- 2026-09-08 · Intersection closure update
Open project →Ingersoll · Parks, recreation & culture
This project represents the construction phase of the MURC. The scope of this work includes full construction of the MURC. This includes structural, mechanical, electrical systems, interior and exterior finishes.
Ingersoll
In Progress- Lifetime project budget
- $38,000,000
- Next target
- No next date listed
- Latest update
- 2026-08-10 · Allocate 2025 operating surplus to Arena Facility Reserve
Open project →Ingersoll · Roads & bridges
Crfwd - 3 Year Bridge Rehab Design Program
Ingersoll
In Progress- 2026 allocation
- $76,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd - Earl St Reconstruction (Ann St to Frances St)
Ingersoll
In Progress- 2026 allocation
- $10,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd - Frances St Reconstruction (Merritt St to Wonham St South) Topcoat
Ingersoll
Procured- 2026 allocation
- $42,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Buildings & facilities
Crfwd - Hall's Creek Retaining Wall Replacement
Ingersoll
In Progress- Revised budget
- $280,000
- Named supplier
- Hohol Enterprises One Limited
- Next target
- 2026-10 · Plannedcompletion
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Parks, recreation & culture
Crfwd - Memorial Park Bandshell
Ingersoll
Completed- 2026 allocation
- $180,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd - Pemberton St Reconstruction (CNR Tracks to North Town Line)
Ingersoll
Not Started- 2026 allocation
- $10,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd - Stormwater Management Strategy Update
Ingersoll
In Progress- 2026 allocation
- $51,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd - Wonham St South Reconstruction (King St to Ann St)
Ingersoll
Procured- 2026 allocation
- $141,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd - Wonham St South Reconstruction Phase I (Ann St to Melita St)
Ingersoll
In Progress- 2026 allocation
- $937,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Crfwd -SWM Pond Asset Performance Assessment and O&M Manuals
Ingersoll
In Progress- 2026 allocation
- $50,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Buildings & facilities
Crfwd -Town Hall - Elevator replacement
Ingersoll
In Progress- 2026 allocation
- $200,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Parks, recreation & culture
The 2024 OSIM inspections identified priority need for maintenance and replacement of Town bridges and culverts exceeding 3 m in diameter. The priority structure maintenance and replacement designs identified by the 2024 OSIM Inspections are for Structure B 22 (Memorial Park over Halls Creek) fo repair of retaining wall and provide erosion protection. Repair deck end cover plates and members with section loss
Ingersoll
In Progress- 2026 allocation
- $40,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Water, drainage & wastewater
The project involves the field topographic survey and subsequent storm drainage solution to intercept storm runoff from the Butternut Park that currently traverses the existing residential lots to the east causing drainage issues and icing conditions on the sidewalk during the winter months. The work will involve the implementation of a swale/ditch to intercept surface runoff and direct this surface flow to a piped storm sewer.
Ingersoll
In Progress- 2026 allocation
- $30,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Buildings & facilities
The 2024 OSIM inspections identify priority needs for maintenance and replacement of Town bridges and culverts exceeding 3 m in diameter. The priority structure maintenance and replacement designs identified in the 2024 OSIM Inspections are for Structure C 18 (Centennial Lane over Halls Creek) for full replacement.
Ingersoll
In Progress- 2026 allocation
- $400,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Roads & bridges
The Transportation Committee received a request for an additional streetlight on Caffyn Street, NE Leg. Town Engineering staff reviewed the area together with ERTH and find that following conventional street lighting, an additional light is warranted.
Ingersoll
Procured- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
Town constructed capital projects generally carry a 2-year warranty and maintenance period. Often, when warranty works are discovered there may be additional costs involved to alter works of varying degrees to provide a better long term solution as opposed to what was initially built and designed. Accommodating an annual allowance will allow such undertakings to be considered on an as needed basis, together with capital warranty work when required.
Ingersoll
In Progress- 2026 allocation
- $10,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
The project involves the replacement of Cast Iron watermain with new PVC watermain, and replacement of sanitary sewers on Charles St from Whiting St to Merritt St by the County of Oxford. Roadworks have a current 63.6 (out of 100) rating making this joint project cost effective for collaborative undertaking. Timescapes camera system will be utilized during construction to monitor construction activities. This is a joint project with the County of Oxford. Length of project is ~410 l.m.
Ingersoll
Not Started- 2026 allocation
- $45,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Roads & bridges
The project involves the replacement of cast iron watermain and sanitary sewer with new PVC piping by the County of Oxford. The Town will replace storm sewers identified by asset management in the roadway. The existing road width will remain the same but new curb and gutters will be placed. New sidewalk will replace the below standard walks currently on the right of way. This is a joint project with the County. Timescapes camera system will be utilized during construction to monitor construction activities Length of project is 150 l.m.
Ingersoll
In Progress- 2026 allocation
- $25,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
The project involves the replacement of cast iron watermain and sanitary sewer with new PVC piping by the County of Oxford. The Town will replace storm sewers identified by asset management in the roadway. The existing road width will remain the same but new curb and gutters will be placed. New sidewalk will replace the below standard walks currently on the right of way. This is a joint project with the County. Timescapes camera system will be utilized during construction to monitor construction activities Length of project is 115 l.m.
Ingersoll
Procured- 2026 allocation
- $17,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
As part of the industry-wide cellular upgrades to the Bell/Rogers networks, the existing GPS handheld controllers have become obsolete and will no longer function under the new 4 G networks by end of 2025. A new GPS Data Collector is required to continue working with the two GNSS (Global Navigation Satellite System) rover units that the Engineering Department already employs. Despite the requirement for the upgrade due to network limitations, the new GPS Data Collectors would provide significant functional improvements to their predecessors, including a larger 7-inch touch display, improved ergonomics, and runs on Windows 10 Pro, enhancing usability and productivity compared to the TSC 3's smaller screen and outdated operating system.
Ingersoll
Completed- 2026 allocation
- $11,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
The project involves the replacement of Cast Iron watermain with new PVC watermain on John Street from Bell Street to the Dead End by the County of Oxford. Roadworks will be updated to municipal standard including concrete curb and gutter and 1.5 m wide concrete sidewalk. Timescapes camera system will be utilized during construction to monitor construction activities This is a joint project with the County of Oxford. Length of project is 230 l.m.
Ingersoll
In Progress- 2026 allocation
- $265,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →Ingersoll · Other projects
The project involves the replacement of Cast Iron watermain with new PVC watermain, and sanitary sewer replacement on John Street from Victoria Street to Bell Street by the County of Oxford. Roadworks will be updated to municipal standard including concrete curb and gutter and 1.5 m wide concrete sidewalk. Timescapes camera system will be utilized during construction to monitor construction activities. This is a joint project with the County of Oxford. Length of project is 160 l.m.
Ingersoll
In Progress- 2026 allocation
- $460,000
- Next target
- No next date listed
- Latest update
- 2026-06-30 · Spending reported through this date
Open project →