03ProjectsIngersoll

Ingersoll · Project

Oxford Road 9 construction in Ingersoll

The latest published plan points to a winter pause, with more work in 2027. A scheduled reopening is not confirmation the road is open.

Money & projects Explore sections
Oxford County projectView County project page →

Before you travel

Oxford County’s October 23 project update plans a November 2026 construction pause, with work restarting in early 2027. It does not confirm that the road has reopened. Continue following posted detours until the road and intersection reopen.

Where the work is happening

The project covers Oxford Road 9 (Hamilton Road/King Street West), from the CPKC railway west to the Town of Ingersoll boundary, including the intersection with Oxford Road 10 (Ingersoll Street South). The winter plan uses an all-way stop at that intersection.

Published detours

  • Main route: Oxford Road 10/Ingersoll Street North, Road 60, Elgin Road and Hamilton Road.
  • Additional intersection route: Oxford Road 10/Ingersoll Street South, Thomas Street and Whiting Street.

Check signs and the current County notice before travelling. This summary is not live navigation and does not establish access to an individual property.

What still needs watching

The 2027 plan includes surface asphalt and restoration. At the Roads 9/10 intersection, planned work includes new curb, sidewalk, traffic signals and street lighting, plus replacement asphalt. That newer plan replaces the earlier December 2026 completion expectation.

Keep three milestones separate: reopening for traffic, restarting construction and finishing the project. Evidence of one does not establish the other two. Look for a stated date, the affected section and remaining restrictions. Do not assume a road reopening also reopens nearby trails.

Read the latest official Oxford Road 9 project update

Check the County’s current construction notices

Official sources checked (UTC). These pages are visitor and project guides, not live condition reports.

At a glance

Original project title

Oxford Road 9: follow the $14.2 million bid into delivery

Location
Ingersoll
Responsible authority
Oxford County
Current stage
November winter pause planned; work resumes early 2027As of 2026-10-22
2026 allocation
Not established
Next target
2026-11 · Planned winter pause and reopening
Named supplier
J-AAR Civil Infrastructures Limited See contract details

The published update schedules a November winter pause, reopening with an all-way stop over winter and resumption in early 2027. The notice gives a planned reopening, not confirmation that the road reopened.

Road, sanitary sewer, watermain, storm sewer, sidewalks, traffic signals, lighting, landscaping and restoration.

Who approves and delivers this project?

Project engineer

Oxford County Public Works

County project page names Michael Holstenson as project engineer and Jesse Keith as Supervisor of Engineering Services.

Money

Project money

Project cost not published in this record.

Latest spending total not published here.

CAD · Project allocation as published; bid HST basis not established · The reviewed 2026 capital schedule does not isolate the full multi-year road and utility project. A 2025 published tender bid is recorded separately.

Timeline

  1. Target date passed; milestone status needs a verified update

    Phase 1 scheduled to start

    Microtunnel sanitary sewer installation scheduled from November 2025 through March 2026.

  2. Superseded historical target

    Phase 2 construction window

    Full reconstruction and utility work scheduled March–December 2026. Historical schedule, superseded by the October 22 winter-pause notice.

  3. work

    Intersection closure update

    County announced a September 14 start week for the Oxford Roads 9 and 10 intersection stage, targeting November completion for that stage.

  4. schedule notice

    Winter-pause schedule published

    November winter pause is planned, with roads reopening and an all-way stop for winter. Detours continue until the actual reopening. Work resumes in early 2027; surface asphalt and restoration are planned for 2027.

  5. review

    Oxford Road 9 winter pause remains planned

    The published update schedules a November winter pause, reopening with an all-way stop over winter and resumption in early 2027. The notice gives a planned reopening, not confirmation that the road reopened.

  6. revised target

    Planned winter pause and reopening

    Scheduled transition, not proof the roads were already open on October 29.

  7. Superseded historical target

    Whole-project target

    December 2026 remains the published completion target; it is not an actual completion date. Historical schedule, superseded by the October 22 winter-pause notice.

  8. revised target

    Early-2027 restart target

    No exact restart or final completion day is established.

Contracts

TENDER-ENG-2025-587 · awardee named in annual register

Oxford Road 9 Urbanization, West of Oxford Road 10 (Ingersoll Road)

J-AAR Civil Infrastructures Limited

Published bid
$14,202,489.13
Published award / contract value
Not established
Unit price
Not established

The published bid does not establish the final executed contract value. Not established in annual register

2025 award connected to current 2026 work. The annual register names the awardee but leaves the contract value and award date unpublished.

Open procurement record

Decisions

No separate decision record is linked. Approval details may appear in the timeline or source documents.

Outcomes

Completion not confirmed.

Questions

  • What is the current approved total across the road, water, sanitary and storm accounts?
  • What is the signed contract value, including approved changes?
  • What has been paid, and what is the updated 2027 completion schedule?

Related issues

Are the promised construction milestones being met, and what happens if they slip?Which level of infrastructure service are we buying, and what risk does a cheaper option leave behind?
Scope & interpretation notes
  • J-AAR Civil Infrastructures Limited is the annual register awardee. Its $14,202,489.13 bid is not a verified executed contract value or project budget.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. County construction projects

    Source ID: county-construction

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    official project notice
    Passage / page
    Named project sections; updates through September 2026

    Open in source library

  2. Oxford Road 9 infrastructure improvements

    Source ID: county-ingersoll-road9-page

    Publisher
    Oxford County
    Published
    2025-10-09
    Reporting period
    2025–2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published record
    Passage / page
    About the project and project contacts
    Evidence notes
    Official page confirms an awarded contract to J-AAR; financial value is not stated.

    Open in source library

  3. 2025 contract award register — TENDER-ENG-2025-587

    Source ID: county-award-tender-eng-2025-587

    Publisher
    Oxford County
    Reporting period
    2025 award register; 2026 active project
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published record
    Passage / page
    TENDER-ENG-2025-587; named awardee and bidder-price row
    Evidence notes
    Prior-year award linked to a project active during 2026. The contract value cell is --; the bid is not a signed contract value.

    Open in source library

  4. Oxford Road 9 — October 22 winter-pause update

    Source ID: county-construction-road9-20261022

    Publisher
    Oxford County
    Source date
    2026-10-22
    Published
    2026-10-22
    Reporting period
    2026
    Reviewed
    2026-10-29
    Retrieved
    2026-10-29
    Verified
    2026-10-29
    Evidence status
    verified_primary
    Decision / approval status
    official source
    Passage / page
    Oxford Road 9 reconstruction, Ingersoll: October 22 update
    Evidence notes
    November winter pause and road reopening are scheduled, not confirmed as completed on October 29. Construction resumes in early 2027; older December 2026 whole-project wording is superseded.

    Open in source library

  5. Oxford Road 9 winter pause remains planned

    Source ID: oct30-or9

    Source date
    2026-10-22
    Event / reporting date
    2026-10-22
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Decision / approval status
    construction; planned winter pause
    Evidence note
    Primary-source body reviewed in the October 30 audit The notice gives a planned reopening, not confirmation that the road reopened.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation