The Town-hosted January 2026 status report says the design-build contract with Ball Construction was signed following Council approval. The exact signing day and executed agreement were not reviewed. This dated report does not establish current construction progress or opening.
This project represents the construction phase of the MURC. The scope of this work includes full construction of the MURC. This includes structural, mechanical, electrical systems, interior and exterior finishes.
Who approves and delivers this project?
Budget and delivery
Town of Ingersoll — Community Services
The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.
Listed funding adds to the lifetime budget amount. Proposed sources are not confirmed receipts. CAD.
Timeline
historical estimate
Historical design and pricing presentation
The December 8, 2025 presentation reports a $37,935,297 guaranteed maximum price for the then-current scope against a $38 million construction budget. Tax basis is unstated. This is historical pricing, not final cost, payment or the full campus and servicing price.
The Town-hosted January 2026 status report says the design-build contract with Ball Construction was signed following Council approval. The exact signing day and executed agreement were not reviewed. This dated report does not establish current construction progress or opening.
The January 2026 Town status report says the Ball Construction design-build contract was signed. The executed agreement and a separate award record were not reviewed; final contract value and payments are not established here.
Current construction milestones, completion, opening and final expenditure have not been established by this review. The unavailable old webpage does not negate the accessible dated project reports.
Questions
What is the current forecast cost and expected completion date?
2026 annual allocation and YTD spending are separate from the $38 m multi-year construction budget. T-008-26 identifies a $56.856 m combined MURC and servicing package. Borrowing authority is not expenditure. The January report’s Q2/Q3 2028 opening and closeout forecasts remain historical, not current commitments.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Mayor’sbudget; Councilshortenedamendmentperiod Jan 12; originalversionpreserved
Passage / page
179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.
Evidence notes
The finance hub now links the 179-page Town Budget PDF dated January 12. Comparison found no substantive numerical change; preserve this earlier version and its sourced figures.
Primary-source body reviewed in the October 30 audit Source check date October 30 live check: Page Not Found. Cached December 2025 text is not current progress.
The report says the Ball Construction contract was signed following Council approval. The cover year says 2025, while the narrative and dashboard establish January 2026. Exact signing day, executed agreement and current construction progress were not verified.
The $37,935,297 guaranteed maximum price is for the then-current scope, compared with the $38 million construction budget. Tax basis is unstated. It is not final expenditure, a payment or the full campus and servicing package.