Ingersoll · Project

Crfwd - Hall's Creek Retaining Wall Replacement

Money & projects Explore sections
Ingersoll project

At a glance

Location
Ingersoll
Responsible authority
Ingersoll
Current stage
In ProgressAs of 2026-06-30
Revised budget
$280,000
Next target
2026-10 · Plannedcompletion
Named supplier
Hohol Enterprises One Limited See contract details

Crfwd - Hall's Creek Retaining Wall Replacement

Retaining wall riprap/concrete protection and localized face repairs; engineering fee $59,684 and construction $214,310.71.

Project 3213

Who approves and delivers this project?

Budget and delivery

Town of Ingersoll — Infrastructure and Development

The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.

Money

Project money

Budget and forecast

Revised published budget
$280,000
Cost forecast
$273,994.71

Annual allocation

2026 allocation
$210,000
2026 capital allocation

Recorded spending

Expenditure through 2026-06-30
$13,221
CAD · Forecast$273,994.71 excludes HST; appropriation$280,000 plus HST · 2026 capital allocation

Where the funding comes from

$210,000Listed funding total

  1. CarryforwardOriginal January 2026 capital funding schedule, physical PDFp 130; funding may be later amended.
    $210,000100% of listed total
Listed funding adds to the 2026 allocation amount. CAD.

Timeline

  1. work

    Previous year-end status

    In progress - to be finished in 2026; cumulative spending through 2025$40,486. Separate from 2026 spending.

  2. Target date passed; milestone status needs a verified update

    Plannedconstructionstart

    Late August as forecast June 8; not a confirmed actual start

  3. original target

    Plannedcompletion

    Early October as forecast June 8; cutoff October 1 does not establish completion

Contracts

RFT6-2026 · Councilawardapproved

Hall’s Creek retaining wall rehabilitation

Hohol Enterprises One Limited · 2026-06-08

Published bid
Not established
Published award / contract value
$214,310.71
Unit price
Not established

Excluding HST; Council minute authorizes total project expenditure plus HST

Award verified in carried Council resolution; no detailed payment register recovered.

Open procurement record

Decisions

Outcomes

Completion not confirmed.

Questions

  • What is the current forecast cost and expected completion date?
Scope & interpretation notes
  • June 30 capital snapshot retains the earlier $210,000 appropriation; June 8 Council raised the project appropriation to $280,000 plus HST. The 2025 closeout separately records a $58,000 earlier phase and $40,486 cumulative spending. These scopes require reconciliation before combining lifetime totals.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2026–2027 Mayor’s Budget

    Source ID: ingersoll-budget-2026

    Publisher
    Town of Ingersoll
    Published
    2026-01-12
    Event / reporting date
    2026-01-12
    Reporting period
    2026–2027
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    Mayor’sbudget; Councilshortenedamendmentperiod Jan 12; originalversionpreserved
    Passage / page
    179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.
    Evidence notes
    The finance hub now links the 179-page Town Budget PDF dated January 12. Comparison found no substantive numerical change; preserve this earlier version and its sourced figures.
    Current version source
    oct29-ingersoll-town-budget-version
    Version checked
    2026-10-29

    Open the current linked version

    Open in source library

  2. T-022-26 — Q 2 operating and capital variance report

    Source ID: ingersoll-q2-2026

    Publisher
    Town of Ingersoll
    Published
    2026-08-10
    Event / reporting date
    2026-08-10
    Reporting period
    sixmonthsended 2026-06-30
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    Received as information; annualbudgetcolumn asreported June 30
    Passage / page
    Capital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52.

    Open in source library

  3. OP-011-26

    Source ID: ingersoll-record-57818

    Publisher
    Town of Ingersoll
    Event / reporting date
    2026-06-08
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published primary record
    Passage / page
    Full public staff report and attached schedules; report number identifies Council agenda item.

    Open in source library

  4. Regular Meeting of Council Minutes - June 8, 2026

    Source ID: ingersoll-record-59124

    Publisher
    Town of Ingersoll
    Event / reporting date
    2026-06-08
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published primary record
    Passage / page
    Public Council minutes; numbered resolutions.

    Open in source library

  5. T-024-26 —2025 capital projects year-end status

    Source ID: ingersoll-capital-close-2025

    Publisher
    Town of Ingersoll
    Published
    2026-08-10
    Event / reporting date
    2026-08-10
    Reporting period
    2025
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published primary record
    Passage / page
    Appendix A: all 50 projects with budget, annual spending, cumulative spending, variance and status.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation