Ingersoll project
On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location Ingersoll
Responsible authority Ingersoll Current stage In ProgressAs of 2026-06-30 Stage and project evidence: [1] [2] [3]
2026 allocation $937,000
Next target No next date listed Crfwd - Wonham St South Reconstruction Phase I (Ann St to Melita St)
Project 3356
Who approves and delivers this project? Budget and delivery
Town of Ingersoll — Infrastructure and Development The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.
Sources for this record: [2]
Money Project money Annual allocation 2026 allocation $937,000 2026 capital allocation CAD · Not separately specified in capital schedule · 2026 capital allocation Project money evidence: [1] [2] [3]
Where the funding comes from $937,000 Listed funding total
Carryforward Original January 2026 capital funding schedule, physical PDFp 130; funding may be later amended. $937,000100% of listed total Listed funding adds to the 2026 allocation amount. CAD. Timeline 2025-12-31 work Previous year-end status Delayed to 2026; cumulative spending through 2025$0. Separate from 2026 spending.
Sources for this record: [3]
Contracts Contract award not confirmed.
Decisions No separate decision record is linked. Approval details may appear in the timeline or source documents.
Outcomes Completion not confirmed.
Questions What is the current forecast cost and expected completion date? Scope & interpretation notes Annual allocation and YTD expense, not lifetime project cost. T-022-26 PDFp 7. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: ingersoll-budget-2026
Publisher Town of Ingersoll
Published 2026-01-12
Event / reporting date 2026-01-12
Reporting period 2026–2027
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status Mayor’sbudget; Councilshortenedamendmentperiod Jan 12; originalversionpreserved
Passage / page 179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.
Evidence notes The finance hub now links the 179-page Town Budget PDF dated January 12. Comparison found no substantive numerical change; preserve this earlier version and its sourced figures.
Current version source oct29-ingersoll-town-budget-version
Version checked 2026-10-29 Open the current linked version
Open in source library
Source ID: ingersoll-q2-2026
Publisher Town of Ingersoll
Published 2026-08-10
Event / reporting date 2026-08-10
Reporting period sixmonthsended 2026-06-30
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status Received as information; annualbudgetcolumn asreported June 30
Passage / page Capital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52. Open in source library
Source ID: ingersoll-capital-close-2025
Publisher Town of Ingersoll
Published 2026-08-10
Event / reporting date 2026-08-10
Reporting period 2025
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status published primary record
Passage / page Appendix A: all 50 projects with budget, annual spending, cumulative spending, variance and status. Open in source library
Copy this view Print