| Town Hall - J. C. Herbert Room RenovationsAccount 3172TOWN HALL | $50,000 | $36,649Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $36,649; unspent $13,351. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Town Hall elevator replacementAccount 3004TOWN HALL | $200,000 | $33,005Through 2025-12-31 | $2,812 | Details & sourceOriginal budget year 2024; cumulative expenditure $35,817; unspent $164,183. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Town Hall - Office RenovationsAccount 3167TOWN HALL | $65,000 | $49,099Through 2025-12-31 | $26,819 | Details & sourceOriginal budget year 2024; cumulative expenditure $75,918; unspent $-10,918. Completed in 2025. Evidence: [1] |
|---|
| Fire Hall - Kitchen ReplacementAccount 3192FIRE | $10,000 | $6,871Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $6,871; unspent $3,129. Completed in 2025. Evidence: [1] |
|---|
| Gear for additional volunteer firefighters (3)Account 3157FIRE | $16,000 | $15,684Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $15,684; unspent $316. Completed in 2025. Evidence: [1] |
|---|
| 3-Year Bridge Rehab Design Program (C 18, B 22, B 20)Account 3345CONSTRUCTION - ROADS & BRIDGES | $105,000 | $43,217Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $43,217; unspent $61,783. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Hall's Creek Retaining Wall ReplacementAccount 3213CONSTRUCTION - ROADS & BRIDGES | $58,000 | $40,486Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $40,486; unspent $17,514. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Sidewalk Rehab or ReplacementAccount 3242CONSTRUCTION - ROADS & BRIDGES | $10,000 | $2,155Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $2,155; unspent $7,845. Completed in 2025. Evidence: [1] |
|---|
| Capital Project Warranty Work AllowanceAccount 3304CONSTRUCTION - ROADS & BRIDGES | $10,000 | $477Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $477; unspent $9,523. Annual Allowance -Not required in 2025. Evidence: [1] |
|---|
| Wonham St South Reconstruction (King St to Ann St)Account 3305CONSTRUCTION - ROADS & BRIDGES | $141,000 | $1,329Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $1,329; unspent $139,671. Delayed to 2026. Evidence: [1] |
|---|
| Frances St Reconstruction (Merritt St to Wonham St South) TopcoatAccount 3306CONSTRUCTION - ROADS & BRIDGES | $42,000 | $0Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $0; unspent $42,000. Delayed to 2026. Evidence: [1] |
|---|
| Carroll St Reconstruction (King St to Charles St) TopcoatAccount 3320CONSTRUCTION - ROADS & BRIDGES | $99,000 | $42,870Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $42,870; unspent $56,130. Completed in 2025. Evidence: [1] |
|---|
| Cherry St Reconstruction (Carrol St to Harris St) TopcoatAccount 3276CONSTRUCTION - ROADS & BRIDGES | $99,000 | $81,932Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $81,932; unspent $17,068. Completed in 2025. Evidence: [1] |
|---|
| John St Reconstruction (Victoria St to Bell St) - GeotechAccount 3322CONSTRUCTION - ROADS & BRIDGES | $50,000 | $9,626Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $9,626; unspent $40,374. Geotech Completed in 2025. Evidence: [1] |
|---|
| John St Reconstruction (Bell St to Dead End) - GeotechAccount 3323CONSTRUCTION - ROADS & BRIDGES | $31,000 | $9,946Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $9,946; unspent $21,054. Geotech Completed in 2025. Evidence: [1] |
|---|
| Wonham St South Reconstruction - Phase II (Melita to Holcroft)Account 3360CONSTRUCTION - ROADS & BRIDGES | $61,000 | $0Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $0; unspent $61,000. Delayed to 2026. Evidence: [1] |
|---|
| Charles St West Reconstruction (Whiting St to Merritt St) - GeotechAccount 3325CONSTRUCTION - ROADS & BRIDGES | $20,000 | $16,951Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $16,951; unspent $3,049. Geotech Completed in 2025. Evidence: [1] |
|---|
| St Andrew St Reconstruction (Mutual St to Thames St) - GeotechAccount 3332CONSTRUCTION - ROADS & BRIDGES | $35,000 | $11,508Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $11,508; unspent $23,492. Geotech Completed in 2025. Evidence: [1] |
|---|
| Wallace Line Reconstruction - Oakwood St to Robinson RoadAccount 3326CONSTRUCTION - ROADS & BRIDGES | $65,000 | $54,956Through 2025-12-31 | $42,212 | Details & sourceOriginal budget year 2024; cumulative expenditure $97,168; unspent $-32,168. Delayed to 2027-2028. Evidence: [1] |
|---|
| Union St Reconstruction - GeotechAccount 3333CONSTRUCTION - ROADS & BRIDGES | $20,000 | $12,776Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $12,776; unspent $7,224. Geotech Completed in 2025. Evidence: [1] |
|---|
| Wonham St South Reconstruction - Phase 1 (Ann St to Melita)Account 3356CONSTRUCTION - ROADS & BRIDGES | $937,000 | $0Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $0; unspent $937,000. Delayed to 2026. Evidence: [1] |
|---|
| Pemberton St Reconstruction (CNR Tracks to North Town Line)Account 3321CONSTRUCTION - ROADS & BRIDGES | $747,000 | $542,646Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $542,646; unspent $204,354. Completed in 2025. Evidence: [1] |
|---|
| Earl St Reconstruction (Ann St to Frances St)Account 3324CONSTRUCTION - ROADS & BRIDGES | $500,000 | $256,073Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $256,073; unspent $243,927. Completed in 2025. Evidence: [1] |
|---|
| Mc Carthy Street - Charles to CherryAccount 3265CONSTRUCTION - ROADS & BRIDGES | $22,000 | $32,505Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $32,505; unspent $-10,505. Completed in 2025. Evidence: [1] |
|---|
| Mc Millan Court Street Light InstallationAccount 3452CONSTRUCTION - ROADS & BRIDGES | $21,000 | $13,411Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $13,411; unspent $7,589. Completed in 2025. Evidence: [1] |
|---|
| Road Needs Study & Parking Lot Inventory Condition AssessmentAccount 3311DEVELOPMENT AND ENGINEERING | $80,000 | $70,784Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $70,784; unspent $9,216. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Clark Road SWM Pond RehabilitationAccount 3344DEVELOPMENT AND ENGINEERING | $255,000 | $158,686Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $158,686; unspent $96,314. Completed in 2025 - carried $$ for misc. fees in 2026. Evidence: [1] |
|---|
| Vehicle Damage Prevention, Monitoring and Protective DeviceAccount 3379DEVELOPMENT AND ENGINEERING | $10,000 | $1,440Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $1,440; unspent $8,560. Completed in 2025. Evidence: [1] |
|---|
| Engineering Department Office UpdatesAccount 3380DEVELOPMENT AND ENGINEERING | $10,000 | $2,200Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $2,200; unspent $7,800. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Stormwater Management Strategy UpdateAccount 3381DEVELOPMENT AND ENGINEERING | $55,000 | $33,374Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $33,374; unspent $21,626. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Replace truck #1 (net of trade in) (2019)Account 3409PUBLIC WORKS | $75,000 | $67,135Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $67,135; unspent $7,865. Completed in 2025. Evidence: [1] |
|---|
| Replace truck #4 (net of trade in) (2015)Account 3400PUBLIC WORKS | $350,000 | $0Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $0; unspent $350,000. Ordered - to be delivered in 2026. Evidence: [1] |
|---|
| Multi Use Rec Facility (MURC)Account VariousPARKS AND RECREATION | $7,475,000 | $2,632,352Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $2,632,352; unspent $4,842,648. In progress - to be completed in 2028. Evidence: [1] |
|---|
| Trails Network (Section 3 & 4)Account 3513PARKS AND RECREATION | $254,000 | $79,950Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $79,950; unspent $174,050. In progress - to be finished in 2026. Evidence: [1] |
|---|
| Memorial Park BandshellAccount 3596PARKS AND RECREATION | $180,000 | $0Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2024; cumulative expenditure $0; unspent $180,000. Delayed to 2026. Evidence: [1] |
|---|
| Jim Robbins Park Playground ReplacementAccount 3514PARKS AND RECREATION | $95,000 | $86,959Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $86,959; unspent $8,041. Completed in 2025. Evidence: [1] |
|---|
| Woodhatch Park Playground ReplacementAccount 3548PARKS AND RECREATION | $95,000 | $88,951Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $88,951; unspent $6,049. Completed in 2025. Evidence: [1] |
|---|
| Creative Arts / VPCC Driveway Retaining Wall RepairsAccount 3563PARKS AND RECREATION | $60,000 | $60,350Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $60,350; unspent $-350. Completed in 2025. Evidence: [1] |
|---|
| Repairs to North & South Diamond OutfieldAccount 3711PARKS AND RECREATION | $15,000 | $14,890Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2025; cumulative expenditure $14,890; unspent $110. Completed in 2025. Evidence: [1] |
|---|
| Flat bed TruckAccount 3599PARKS AND RECREATION | $85,000 | $81,820Through 2025-12-31 | $0 | Details & sourceOriginal budget year 2024; cumulative expenditure $81,820; unspent $3,180. Carry Forward from 2024 -Completed in 2025. Evidence: [1] |
|---|